Property Factors Code of Conduct: Repairs, Quotes and Contractor Appointments

Ask any factor where homeowner complaints start, and repairs will be near the top of the list. Why that contractor? Why so expensive? Why did nobody tell us the work had been cancelled? In Scotland, the Code of Conduct for Property Factors gives these questions a whole section of their own. Section 6 sets out how repairs and maintenance should be handled, and the revised version has applied since 16 August 2021.

This guide covers what Section 6 actually asks for, the paperwork worth keeping on every job, and what happens if a homeowner takes a complaint to the tribunal.

What Section 6 asks for

Section 6 has twelve paragraphs. These are the ones that shape day-to-day work:

ParagraphWhat it requires
6.3A procedure for homeowners to report repairs
6.4Work carried out within an appropriate timescale, with homeowners kept informed of progress and the estimated completion date
6.6A range of options considered, cost balanced against quality and longevity, and the ability to show how and why a contractor was appointed, provided on request
6.8Reasonable steps to make sure contractors hold public liability insurance
6.9Tendering or contractor selection documents available to homeowners on request (commercially sensitive information excepted)
6.10Written disclosure of any commission, fee, rebate or other benefit linked to a contract
6.11Written disclosure of any financial or other interest in the contractors you appoint
6.12On request, liaising with the contractor to put defective work right

The three paragraphs that are hardest to prove

6.6: the "how and why". The Code doesn't tell you how many quotes to get. It does expect you to be able to explain the decision. "We used them because we always use them" won't hold up six months later. What holds up is what you wrote down at the time: the options on the table, what each one cost and why you picked the one you did.

6.8: insurance. Reasonable steps means, at the very least, having seen the policy and checked it was in date when you instructed the work. Seeing it last year isn't the same thing.

6.10 and 6.11: commission and interests. Both need a written disclosure. If there's no commission and no connection, it's still worth recording that, so there's no doubt later.

Before the work: authority and thresholds

Section 1 asks for your written statement of services to set out, where it applies, any delegated authority you hold, including the financial thresholds for instructing works and the situations where you can act without consulting homeowners again. Paragraph 2.6 then asks for a procedure to consult homeowners and get their consent before work that costs more than the core service. The exceptions are a delegated authority agreed in writing up to a set amount, or situations such as emergencies where homeowners have agreed you can act without further approval.

If your thresholds aren't clear, every repair above a few hundred pounds becomes a potential argument. Settle them first.

When a homeowner complains

Under the Property Factors (Scotland) Act 2011, a homeowner must first tell you in writing why they think you've failed in your duties (section 17). If you refuse to resolve it, or take unreasonably long, they can apply to the tribunal. Since 1 December 2016 that has been the First-tier Tribunal for Scotland (Housing and Property Chamber).

If the tribunal finds a failure, it can make a property factor enforcement order (sections 19 and 20). The order sets out the action you must take and, where appropriate, a payment to the homeowner, with a deadline. Failing to comply without a reasonable excuse is a criminal offence (section 24). The Chamber publishes its decisions online, so they're there for anyone to read.

When a complaint does arrive, whether you can deal with it in an afternoon or spend weeks on it usually comes down to one thing: whether the paperwork for that job exists and you can find it.

What to keep for every job

A practical checklist covering paragraphs 6.4 to 6.11:

  1. The quote request: who you asked, when, and the deadline you gave them.
  2. The quotes you received, itemised, with how long they're valid.
  3. The decision: who got the job and why. If you only had one quote, why you didn't look for more.
  4. The contractor's insurance, checked on the day you appointed them.
  5. Your declaration of commission and interests, even if the answer is "none".
  6. Progress updates and what you told homeowners.
  7. Before and after photos, and confirmation that the work was signed off.
  8. The invoice against what you agreed, with an explanation for any difference.

How PropLinker handles it

In PropLinker, every award creates an Appointment Record. It can't be edited after the fact, and it keeps the quotes considered, the reason for the choice, the justification if no other quotes were sought, the declaration of commission or interests, and the status of the contractor's insurance on that day. If the insurance has expired or isn't on file, PropLinker asks you to record a reason before you can go ahead.

Contractors reply to quote requests from a link in the email, with no account needed. If they sign up (it's free for them), they can follow the job from their own portal, add timestamped before and after photos, and send their invoice as a PDF. If the total doesn't match what was awarded, they have to explain the difference, and you have to accept it explicitly before the invoice can be approved.

To be clear, PropLinker doesn't guarantee compliance with the Code. What it does is make sure every decision is written down at the time, so you can show it when someone asks.

If you're comparing tools, our guide to property factor software in Scotland covers the rest of the day-to-day work, and managing agents vs Scottish factors explains how the two regimes differ. The Contractor Portal is included in every plan.


Sources: Scottish Government, Code of Conduct for Property Factors (2021), Section 6, Section 1 and Section 2 · Property Factors (Scotland) Act 2011, Explanatory Notes · The First-tier Tribunal for Scotland (Transfer of Functions of the Homeowner Housing Panel) Regulations 2016 · Housing and Property Chamber